Monday, 6 January 2025

Visit-On-Site Progress and Challenges

The team visited the BN004 site, where the mason arrived to begin work at the same time. BN004 was also present at the site, accompanied by some neighbours. We conducted a thorough assessment to evaluate the progress that had been made on the project.

Key developments included the delivery of the door the previous day, as well as the completion of significant construction milestones. The walls of the toilet building were fully plastered on both the inside and outside, and the roof timbers had been successfully installed. Additionally, the three toilet pit plates had dried completely. However, it was noted that the pit had accumulated a substantial amount of rainwater, which would need to be addressed soon to avoid delays in the pit work.

During the site review, the mason highlighted a few issues that needed attention. He noted that the bolts delivered on Sunday were too long and would need to be replaced with 4.5-inch bolts. He also requested red cement powder to mix with the cement for the toilet floor. In addition, the mason inquired about the delivery of the spotting pan. We informed him that we would visit Jaffna town to purchase the spotting pan and deliver it, along with the other required items, upon our return.

No comments:

Post a Comment

Site Visit: Potential Toilet Beneficiary

Site Visit for Potential Toilet Beneficiary Tuesday, 19th August 2025 – 11.30am On Tuesday, 19th August 2025,  Also accompanying us were...