Visit-Preparation Work for Toilet Foundation

Team arrived on-site.  Mason and BN004 relative were working, they had cleared and prepared the area for the toilet construction.  The Mason measured and marked out the toilet area after reviewing the toilet drawing. Work then began with BN004 relative, who had agreed to dig out the foundation area for the toilet. The Mason focused on making the framework for the toilet pit plates from the metal rods.  Pictures were taken to document the materials delivered and the work in progress. 