Friday, 18 July 2025

Delivery: BN005 Construction Update – Nearing Completion

This afternoon, we received a call from site BN005 requesting an urgent delivery of sand to continue construction of the toilet facility. With completion scheduled for this weekend, we were disappointed not to have been informed earlier of the material shortage.

To avoid any delays, we acted quickly and were able to arrange a Landmaster delivery through our local supplier, who kindly accommodated us despite the short notice.

A team member visited the site to assess progress and capture photos. We're pleased to report that the toilet walls have now been fully constructed and the roof has also been completed.

We have advised BN005 that the squatting pan and accessories will be delivered on Saturday, 19th July 2025. The project is on track and nearing completion.