Saturday, 22 February 2025

Call Made: Update on BN004: Water Level Progress and Work Schedule

This morning, a call was made to BN004 for an update on the ongoing work. The mason answered and provided some positive news, stating that most of the water had subsided. However, he mentioned that he was currently working in Vavuniya and would be unable to continue the work until the end of the week.

Given that rain was forecast by the end of the week, we advised him to consider arranging for someone to continue the work in his absence. The mason acknowledged the situation and stated that he would inform us if it was possible to make such arrangements.

We will follow up to ensure the work continues as planned and monitor any developments regarding the weather and work schedule. 

No comments:

Post a Comment

Site Visit: Potential Toilet Beneficiary

Site Visit for Potential Toilet Beneficiary Tuesday, 19th August 2025 – 11.30am On Tuesday, 19th August 2025,  Also accompanying us were...